Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

CompTIA Project+ Certification (2026) PK0-005 Question # 130 Topic 14 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 130 Topic 14 Discussion

PK0-005 Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?


A.

Data plan


B.

Contingency plan


C.

Rollback plan


D.

Recovery plan


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.