A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?
The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to accomplish project objectives. If tasks can be broken into smaller deliverables, the WBS should be updated first to reflect these changes.
According to the CompTIA Project+ PK0-005 exam objectives, under Domain 2.2: Given a scenario, determine the appropriate scope management activities, maintaining an accurate WBS is crucial for effective scope management.