CompTIA Project+ Certification (2025) PK0-005 Question # 88 Topic 9 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 88 Topic 9 Discussion

PK0-005 Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?


A.

Document the request in the change control log.


B.

Communicate the change deployment.


C.

Conduct an impact assessment.


D.

Implement the change.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.