CompTIA Project+ Certification (2025) PK0-005 Question # 68 Topic 7 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 68 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?


A.

Too much time might be spent generating project delays.


B.

The project manager might be seen as weak.


C.

The number of change requests throughout the project might be reduced.


D.

Some stakeholders might not be completely satisfied.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.