CompTIA Project+ Certification (2026) PK0-005 Question # 67 Topic 7 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 67 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?


A.

Change the precedence of the tasks to " finish-to-start " .


B.

Evaluate and modify the schedule with a burndown chart


C.

Assign additional resources to prevent overwork.


D.

Perform critical path analysis