Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2026) PK0-005 Question # 69 Topic 7 Discussion

CompTIA Project+ Certification (2026) PK0-005 Question # 69 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?


A.

Removing access


B.

Closing contracts


C.

Project sign-off


D.

Project evaluation


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.