New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 69 Topic 7 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 69 Topic 7 Discussion

PK0-005 Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?


A.

Change log


B.

Project Gantt


C.

Issue log


D.

Requirements traceability matrix


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.