CompTIA Project+ Certification (2025) PK0-005 Question # 79 Topic 8 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 79 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?


A.

9 days and $3,000


B.

10 days and $3,200


C.

12 days and $3,800


D.

14 days and $4,000


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.