Question #: 71
Topic #: 8

Which of the following best describes the difference between the current state and the desired future state in project management?


A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.


B.

The current state is where the business is now, and the desired state is where the project is going to take the business.


C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.


D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.