PK0-005 Exam Topic 8 Question 71 Discussion:
Question #: 71
Topic #: 8

A company plans to install new servers. The project manager receives a notification that the manufacturer may be in financial trouble, so the servers will be sourced from another vendor. Which of the following risk management strategies should the project manager use?


A.

Share


B.

Exploit


C.

Mitigate


D.

Avoid