CompTIA Project+ Certification (2025) PK0-005 Question # 74 Topic 8 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 74 Topic 8 Discussion

PK0-005 Exam Topic 8 Question 74 Discussion:
Question #: 74
Topic #: 8

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?


A.

Trigger the contingency plan and communicate with the stakeholders.


B.

Work with the functional managers to create a work-around.


C.

Submit a change request to the change control board.


D.

Transfer the risk by hiring a new vendor who was successful on a previous project.


E.

Set up an escalation meeting with the sponsor.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.