Question #: 80
Topic #: 9

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?


A.

Exploit


B.

Share


C.

Transfer


D.

Accept