Pass the AACE International Professional Level Certifications PSP Questions and answers with CertsForce

Viewing page 4 out of 5 pages
Viewing questions 31-40 out of questions
Questions # 31:

How much Total Float does drafting the product manual have?

Question # 31

Options:

A.

15 workdays.


B.

0 workdays.


C.

10 workdays.


D.

5 workdays.


Expert Solution
Questions # 32:

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed


B.

date the project manager turns in the schedule update


C.

system date when the software calculates the update


D.

date on which progress is based


Expert Solution
Questions # 33:

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

Options:

A.

Project objectives in terms of cost, schedule and quality measures


B.

Project contract between the contractor and owner


C.

Project justification


D.

Project deliverables


Expert Solution
Questions # 34:

How many workdays occur from the start of the Product Testing to the Product Available milestone?

Options:

A.

70


B.

100


C.

60


D.

90


Expert Solution
Questions # 35:

What portion of Activity B is on the critical path?

Options:

A.

Last half of the activity


B.

None of it


C.

First half of the activity


D.

The whole activity


Expert Solution
Questions # 36:

What is a key first step in developing a critical path method schedule?

Options:

A.

Drawing a bar chart of the key phrases of the work.


B.

Defining the execution plan to meet the required scope of work.


C.

Setting out the resource to be used and its limitations.


D.

Drawing the logic diagram.


Expert Solution
Questions # 37:

These are the activities on the critical path:

Question # 37

Options:

A.

A, D, & I.


B.

A, C, E, & H.


C.

A, B, G, & H.


D.

A, B, F, & J


Expert Solution
Questions # 38:

How could the structural steel drawing delay have been prevented?

Options:

A.

Add a time buffer at the end of structural steel activities.


B.

Allow adequate time for review and resubmittal in the baseline schedule.


C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.


D.

Switch to post-tensioned concrete construction.


Expert Solution
Questions # 39:

Identify the minimum project duration.

Question # 39

Options:

A.

20 months.


B.

16 months.


C.

19 months.


D.

21 months.


Expert Solution
Questions # 40:

Determine the correct formula and date for the late start for Activity 9001.

Question # 40

Options:

A.

The early finish is required in order to determine the answer.


B.

LS.6001 Dur.6001 -> 11-20-02.


C.

There is insufficient data provided to calculate the answer.


D.

LF.9001 Dur.9001 -> 11-20-02.


Expert Solution
Viewing page 4 out of 5 pages
Viewing questions 31-40 out of questions