Questions # 11:

What problems can a soils engineer deal with on a project?

Options:

A.

Survey error.


B.

Hidden subsurface conditions.


C.

Archeological findings.


D.

Toxic soils.


Expert Solution
Questions # 12:

What method offers the best chance of the schedule being used effectively to implement the project in the field?

Options:

A.

Issue detailed schedule updates as frequently as possible.


B.

Obtain consent and agreement to the schedule from the key project personnel.


C.

Include detailed and stringent set of scheduling specifications in the contract.


D.

Allow large time contingencies on milestones and completion deadlines.


Expert Solution
Questions # 13:

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

Options:

A.

263 CY


B.

368 CM


C.

201 CY


D.

306 CY


Expert Solution
Questions # 14:

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Question # 14

Options:

A.

1001, 2001, 2002, 2003


B.

2001, 2002, 2003, 2007


C.

1001, 2002, 2003


D.

1001, 2002, 2002, 2003, 3001


Expert Solution
Questions # 15:

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600


B.

S12.990.000


C.

S13.102.900


D.

S12.953.600


Expert Solution
Questions # 16:

If Activity E's duration changes to 4 months, what is the overall duration of the project.

Question # 16

Options:

A.

19 months.


B.

20 months.


C.

22 months.


D.

21 months.


Expert Solution
Questions # 17:

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

Question # 17

Options:

A.

Delay product release by 5 days.


B.

Expedite packaging by 5 days.


C.

Expedite printing by 5 days.


D.

Delay manufacturing by 5 days.


Expert Solution
Questions # 18:

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Options:

A.

It is calculated using the original logic.


B.

It is calculated using logic reflecting out-of-sequence progress.


C.

An out-of-sequence activity cannot resume until all predecessors are finished.


D.

There is no such thing.


Expert Solution
Questions # 19:

What is the remaining work duration of Active D?

Question # 19

Options:

A.

4.


B.

11


C.

8.


D.

3.


Expert Solution
Questions # 20:

Resource planning must take all of the following into account except for:

Options:

A.

Types of materials, equipment and labor skills required to complete the project.


B.

Earned value techniques established for the project.


C.

Time available to complete the project.


D.

Cash flow (expenditure) limitations for completing work on the project.


Expert Solution