Pass the AACE International Professional Level Certifications PSP Questions and answers with CertsForce

Viewing page 5 out of 5 pages
Viewing questions 41-50 out of questions
Questions # 41:

The work breakdown structure is used to organize

Options:

A.

"Smart activity ID codes" representing similar items of scheduled work


B.

The chart of accounts


C.

Similar activity coding of schedule activities


D.

The smallest defined work packet


Expert Solution
Questions # 42:

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.

Claims and disputes phase.


B.

Installation phase.


C.

Planning and design phase.


D.

Turnover and start-up phase.


Expert Solution
Questions # 43:

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.

Not suitable for complicated projects with multiple planned critical paths.


B.

Accuracy is increased by inserting delaying events into the as-planned schedule.


C.

Not suitable for projects with long durations.


D.

Less accurate as the analysis advances through the project.


Expert Solution
Questions # 44:

Which of the following is NOT required when performing weekly or monthly schedule updates?

Options:

A.

Percent complete.


B.

Remaining duration of activities.


C.

Actual finish of activities.


D.

Original duration of activities.


Expert Solution
Questions # 45:

Which activity is drawn in the incorrect position?

Question # 45

Options:

A.

Activity G.


B.

Activity E.


C.

Activity C.


D.

Activity D.


Expert Solution
Questions # 46:

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size


B.

Estimated labor hours


C.

Hours in a standard work day


D.

Estimated cost


Expert Solution
Questions # 47:

Which of the following is NOT true?

Options:

A.

Remaining durations can exceed original durations.


B.

Constraints can interfere with the longest path calculation.


C.

Multiple calendars can affect the total float calculation.


D.

A network must contain only one Critical Path.


Expert Solution
Questions # 48:

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

Options:

A.

Expedite Draft Product Manual by 5 days


B.

Delay Release for Manufacture by 5 days


C.

Delay Manufacture Product by 5 days


D.

Expedite Package Product by 5 days


Expert Solution
Viewing page 5 out of 5 pages
Viewing questions 41-50 out of questions