Pass the PMI Project-Management-Professional PMI-001 Questions and answers with CertsForce

Viewing page 11 out of 14 pages
Viewing questions 201-220 out of questions
Questions # 201:

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,


B.

Final products or services,


C.

Document updates,


D.

Work performance information.


Expert Solution
Questions # 202:

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

Options:

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)


B.

Cost-Reimbursable Contract (CR)


C.

Firm-Fixed -Price Contract (FFP)


D.

Fixed-Price-Incentive-Fee Contract (FPIF)


Expert Solution
Questions # 203:

Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?

Options:

A.

Close Procurements


B.

Administer Procurements


C.

Plan Procurements


D.

Conduct Procurements


Expert Solution
Questions # 204:

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan


B.

Develop Project Charter


C.

Direct and Manage Project Execution


D.

Collect Requirements


Expert Solution
Questions # 205:

The person assigned by the performing organization to be responsible for achieving the project objectives is the:

Options:

A.

functional manager


B.

program manager


C.

project manager


D.

portfolio manager


Expert Solution
Questions # 206:

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000


B.

US$9500


C.

US$10,000


D.

US$12,500


Expert Solution
Questions # 207:

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach


B.

Early, in public, using an indirect, collaborative approach


C.

Early, in private, using an indirect, cooperative approach


D.

As late as possible, in public, using a direct, confrontational approach


Expert Solution
Questions # 208:

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7


B.

8


C.

14


D.

16


Expert Solution
Questions # 209:

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing


B.

Fast tracking


C.

Leads and lags adjustment


D.

Parallel task development


Expert Solution
Questions # 210:

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

Options:

A.

training, testing, and warranty work.


B.

equipment, rework, and scrap.


C.

training, document processes, and inspections.


D.

inspections, rework, and warranty work.


Expert Solution
Questions # 211:

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit


B.

Lessons learned


C.

Performance reporting


D.

Payment requests


Expert Solution
Questions # 212:

An output of the Close Project (or Close Phase) process is:

Options:

A.

accepted deliverables


B.

organizational process asset updates


C.

work performance information


D.

project management plan updates


Expert Solution
Questions # 213:

Which of the following is an output of Close Procurements?

Options:

A.

Accepted deliverables


B.

Organizational process assets updates


C.

Managing stakeholder expectations


D.

Performance reports


Expert Solution
Questions # 214:

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio


B.

Process


C.

Project


D.

Program


Expert Solution
Questions # 215:

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

Options:

A.

Team meetings


B.

Subcontracting teams


C.

Virtual teams


D.

Teamwork


Expert Solution
Questions # 216:

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Options:

A.

Close Project or Phase


B.

Conduct Procurements


C.

Control Procurements


D.

Close Procurements


Expert Solution
Questions # 217:

Types of internal failure costs include:

Options:

A.

inspections.


B.

equipment and training.


C.

lost business.


D.

reworking and scrapping.


Expert Solution
Questions # 218:

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising


B.

Collaborating


C.

Smoothing


D.

Problem Solving


Expert Solution
Questions # 219:

During which process would you obtain stakeholders’ formal acceptance of the completed project scope?

Options:

A.

Quality control


B.

Scope verification


C.

Scope control


D.

Close project


Expert Solution
Questions # 220:

Which Knowledge Areas include processes from the Closing Process Group?

Options:

A.

Project Quality Management and Project Time Management


B.

Project Scope Management and Project Risk Management


C.

Project Stakeholder Management and Project Cost Management


D.

Project Integration Management and Project Procurement Management


Expert Solution
Viewing page 11 out of 14 pages
Viewing questions 201-220 out of questions