PMI-001 Exam Topic 22 Question 210 Discussion:
Question #: 210
Topic #: 22

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:


A.

training, testing, and warranty work.


B.

equipment, rework, and scrap.


C.

training, document processes, and inspections.


D.

inspections, rework, and warranty work.