PMI Project Management Professional v5 PMI-001 Question # 211 Topic 22 Discussion

PMI Project Management Professional v5 PMI-001 Question # 211 Topic 22 Discussion

PMI-001 Exam Topic 22 Question 211 Discussion:
Question #: 211
Topic #: 22

Which organizational process assets update is performed during the Close Procurements process?


A.

Procurement audit


B.

Lessons learned


C.

Performance reporting


D.

Payment requests