PMI-001 Exam Topic 21 Question 209 Discussion:
Question #: 209
Topic #: 21

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?


A.

Crashing


B.

Fast tracking


C.

Leads and lags adjustment


D.

Parallel task development