PMI Project Management Professional v5 PMI-001 Question # 208 Topic 21 Discussion

PMI Project Management Professional v5 PMI-001 Question # 208 Topic 21 Discussion

PMI-001 Exam Topic 21 Question 208 Discussion:
Question #: 208
Topic #: 21

What is the number of stakeholders, if the project has 28 potential communication channels?


A.

7


B.

8


C.

14


D.

16