Questions # 241:

Which provides the basic framework for managing a project?

Options:

A.

Project life cycle


B.

Work breakdown structure (WBS)


C.

Enterprise environmental factors


D.

Project initiation


Expert Solution
Questions # 242:

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities


B.

Estimate Activity Durations


C.

Estimate Activity Resources


D.

Sequence Activities


Expert Solution
Questions # 243:

A contract management plan is a subsidiary of what other type of plan?

Options:

A.

Resource plan


B.

Project management plan


C.

Cost control plan


D.

Expected monetary value plan


Expert Solution
Questions # 244:

Which type of organizational structure is displayed in the diagram provided?

Question # 244

Options:

A.

Balanced matrix


B.

Projectized


C.

Strong matrix


D.

Functional


Expert Solution
Questions # 245:

Which of the following is a tool and technique for activity duration estimating?

Options:

A.

Parametric estimating


B.

Monte Carlo analysis


C.

Top-down estimating


D.

Bottom-up estimating


Expert Solution
Questions # 246:

Inputs to the Plan Risk Management process include the:

Options:

A.

cost management plan.


B.

risk management plan,


C.

activity list,


D.

risk register.


Expert Solution
Questions # 247:

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team


B.

Acquire Project Team


C.

Develop Project Team


D.

Plan Human Resource Management


Expert Solution
Questions # 248:

During what process is the quality policy determined?

Options:

A.

Initiating


B.

Executing


C.

Planning


D.

Controlling


Expert Solution
Questions # 249:

An input to the Create WBS process is a:

Options:

A.

project charter.


B.

stakeholder register.


C.

project scope statement.


D.

requirements traceability matrix.


Expert Solution
Questions # 250:

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

Options:

A.

updates.


B.

defect repairs.


C.

preventive actions.


D.

corrective actions.


Expert Solution
Questions # 251:

An input to the Plan Cost Management process is:

Options:

A.

Cost estimates.


B.

Resource calendars,


C.

The project charter,


D.

The risk register.


Expert Solution
Questions # 252:

Which is an input to the Verify Scope process?

Options:

A.

Performance report


B.

Work breakdown structure (WBS)


C.

Requested changes


D.

Project management plan


Expert Solution
Questions # 253:

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

Options:

A.

Develop Schedule


B.

Create VVBS


C.

Estimate Activity Resources


D.

Define Scope


Expert Solution
Questions # 254:

What is the total float of the critical path?

Options:

A.

Can be any number


B.

Zero or positive


C.

Zero or negative


D.

Depends on the calendar


Expert Solution
Questions # 255:

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.


B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.


C.

all projects undertaken by a company.


D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.


Expert Solution
Questions # 256:

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis


Expert Solution
Questions # 257:

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.


B.

Develop Project Charter.


C.

Develop Schedule.


D.

Plan Scope Management.


Expert Solution
Questions # 258:

When should quality planning be performed?

Options:

A.

While developing the project charter


B.

In parallel with the other planning processes


C.

As part of a detailed risk analysis


D.

As a separate step from the other planning processes


Expert Solution
Questions # 259:

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work


B.

Resource calendars


C.

Procurement document


D.

Independent estimates


Expert Solution
Questions # 260:

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

Options:

A.

Communications management plan


B.

Human resource plan


C.

Quality management plan


D.

Procurement management plan


Expert Solution