PMI Project Management Professional v5 PMI-001 Question # 259 Topic 26 Discussion

PMI Project Management Professional v5 PMI-001 Question # 259 Topic 26 Discussion

PMI-001 Exam Topic 26 Question 259 Discussion:
Question #: 259
Topic #: 26

Which is used to solicit proposals from prospective sellers?


A.

Procurement statement of work


B.

Resource calendars


C.

Procurement document


D.

Independent estimates