Question #: 260
Topic #: 27

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?


A.

Communications management plan


B.

Human resource plan


C.

Quality management plan


D.

Procurement management plan