Question #: 261
Topic #: 27

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?


A.

The customer and functional managers


B.

The risk owners and stakeholders


C.

The sponsors and stakeholders


D.

The project management team