PMI Project Management Professional v5 PMI-001 Question # 243 Topic 25 Discussion

PMI Project Management Professional v5 PMI-001 Question # 243 Topic 25 Discussion

PMI-001 Exam Topic 25 Question 243 Discussion:
Question #: 243
Topic #: 25

A contract management plan is a subsidiary of what other type of plan?


A.

Resource plan


B.

Project management plan


C.

Cost control plan


D.

Expected monetary value plan