Questions # 221:

The following is a network diagram for a project.

Question # 221

The free float for Activity E is how many days?

Options:

A.

2


B.

3


C.

5


D.

8


Expert Solution
Questions # 222:

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets


B.

Histograms


C.

Flowcharts


D.

Control charts


Expert Solution
Questions # 223:

An input to the Plan Stakeholder Management process is:

Options:

A.

The project charter.


B.

The stakeholder analysis.


C.

A communication management plan.


D.

A stakeholder register.


Expert Solution
Questions # 224:

At which stage of the project should certain factors such as the unavailability of human resources due to constraint be considered?

Options:

A.

Initiation


B.

Execution


C.

Planning


D.

Monitoring and Controlling


Expert Solution
Questions # 225:

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.


B.

establishes project roles and responsibilities.


C.

improves teamwork, interpersonal skills, and competencies.


D.

provides an accurate appraisal of team member performance.


Expert Solution
Questions # 226:

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management


B.

Control Procurements


C.

Collect Requirements


D.

Plan Cost Management


Expert Solution
Questions # 227:

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating


B.

Monitoring and Controlling


C.

Planning


D.

Closing


Expert Solution
Questions # 228:

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment


B.

Roles and responsibilities


C.

Staffing management plan


D.

Enterprise environmental factors


Expert Solution
Questions # 229:

The Create WBS process is in which of the following Project Management Process Groups?

Options:

A.

Planning


B.

Monitoring and Controlling


C.

Executing


D.

Initiating


Expert Solution
Questions # 230:

When can pre-assignment of project team members occur?

Options:

A.

When the project uses capital expenditures


B.

When the required staff can be acquired from outside sources


C.

When the project would be ignored due to travel expenses


D.

When the project is the result of specific people being promised as part of a competitive proposal


Expert Solution
Questions # 231:

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates


B.

Project management plan updates and enterprise environmental factor updates


C.

Resource calendars and project management plan updates


D.

Team performance assessments and enterprise environmental factor updates


Expert Solution
Questions # 232:

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure


B.

Organizational breakdown structure


C.

Resource breakdown structure


D.

Bill of materials


Expert Solution
Questions # 233:

"Tailoring" is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.


B.

act of creating a project team with the specialized skills required to produce a required product or service.


C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.


D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.


Expert Solution
Questions # 234:

A tool and technique used during the Create WBS process is:

Options:

A.

decomposition


B.

expert judgment


C.

inspection


D.

variance analysis


Expert Solution
Questions # 235:

An output of the Create WBS process is:

Options:

A.

Scope baseline.


B.

Project scope statement.


C.

Organizational process assets.


D.

Requirements traceability matrix.


Expert Solution
Questions # 236:

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.


B.

How a change to the independent variable influences the value of the dependent variable.


C.

The upper and lower specification limits on a control chart.


D.

The central tendency, dispersion, and shape of a statistical distribution.


Expert Solution
Questions # 237:

What defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan


B.

Evaluation criteria


C.

Work Breakdown Structure (WBS)


D.

Contract Statement of Work (SOW)


Expert Solution
Questions # 238:

Which tool or technique is used in the Plan Scope Management process?

Options:

A.

Document analysis


B.

Observations


C.

Product analysis


D.

Expert judgment


Expert Solution
Questions # 239:

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan


B.

Quality management plan


C.

Communications management plan


D.

Risk management plan


Expert Solution
Questions # 240:

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan


B.

Activity resource requirements


C.

Resource calendar


D.

Project staff assignments


Expert Solution