New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional v5 PMI-001 Question # 227 Topic 23 Discussion

PMI Project Management Professional v5 PMI-001 Question # 227 Topic 23 Discussion

PMI-001 Exam Topic 23 Question 227 Discussion:
Question #: 227
Topic #: 23

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?


A.

Initiating


B.

Monitoring and Controlling


C.

Planning


D.

Closing


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.