PMI Project Management Professional v5 PMI-001 Question # 215 Topic 22 Discussion

PMI Project Management Professional v5 PMI-001 Question # 215 Topic 22 Discussion

PMI-001 Exam Topic 22 Question 215 Discussion:
Question #: 215
Topic #: 22

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?


A.

Team meetings


B.

Subcontracting teams


C.

Virtual teams


D.

Teamwork


Get Premium PMI-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.