Questions # 51:

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?

Options:

A.

Tell the technical lead to do the testing


B.

Facilitate an open and focused team discussion that reinforces team agreements


C.

Ask the team manager to advise the technical lead that all tasks are important


D.

Encourage the team to take ownership of the delivery


Expert Solution
Questions # 52:

What should the agile practitioner do?

Options:

A.

Ask the product owner to inform all stakeholders about the project's progress.


B.

Send meeting notes to all stakeholders after each review meeting.


C.

Include the results of the review meetings in the information radiators.


D.

Convince the stakeholders of the benefits of attending the review meetings.


Expert Solution
Questions # 53:

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.

How should the team lead address this?

Options:

A.

Inform management and suggest that additional resources may be required


B.

Discuss the issue with the team in the daily stand-up meetings


C.

Meet personally with the stressed team member to brainstorm ways to better manage their time


D.

Begin tracking the stressed team member's tasks in a separate backlog for additional analysis and reporting


Expert Solution
Questions # 54:

An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

Options:

A.

Leverage continuous feedback from customers to seamlessly align delivery with requirements.


B.

Define software functionality by relying on the developers' experience designing similar system


C.

Engage end users in user acceptance testing to ensure the product meets their expectations.


D.

Educate end users and other stakeholders to understand desired outcomes through user stories.


Expert Solution
Questions # 55:

What should the agile project manager do?

Options:

A.

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.


B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.


C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.


D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.


Expert Solution
Questions # 56:

What should the Scrum Master do?

Options:

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope


B.

Work with the customer to narrow the scope


C.

Share the project's trajectory with the legal department


D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables


Expert Solution
Questions # 57:

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

Options:

A.

Add the releases into a roadmap with milestones and activities.


B.

Identity dedicated tasks and activities with regular feedback loops.


C.

Deliver in small and continuous iterative releases.


D.

Identify the requirements' schedule within set time scales.


Expert Solution
Questions # 58:

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

Options:

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.


B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.


C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.


D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.


Expert Solution
Questions # 59:

A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.

How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?

Options:

A.

Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.


B.

Ask the product owner to review their items with the product owner's teammates before adding user stories to the backlog.


C.

Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.


D.

Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.


Expert Solution
Questions # 60:

What should the project leader suggest?

Options:

A.

Develop and document a detailed architectural design; peer review with the development team and implement/test


B.

Develop the functional requirements of the solution first before any non-functional requirement, as they provide more customer value


C.

Discuss the integration requirement with the product owner and negotiate it to be lower on the backlog to focus on the minimal marketable feature


D.

Develop and test the implementation approach and demonstrate it at the next sprint review to collect feedback