Questions # 61:

What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

Options:

A.

Invite people from across the organization to attend daily stand-ups


B.

Invite people from across the organization to attend retrospectives


C.

Invite people from across the organization to attend the release meeting and project retrospectives


D.

Regularly meet with people across the organization to share the project's lessons learned and best practices


Expert Solution
Questions # 62:

What should the agile coach tell the team?

Options:

A.

Continuing to track velocity allows functional managers to assess whether or not the team is performing at the desired rate.


B.

The trends will show how the team performs against other Scrum teams in the organization.


C.

Tracking velocity will provide a baseline for the team to see how their continuous improvement efforts are working.


D.

Tracking velocity will document and communicate team health to the stakeholders.


Expert Solution
Questions # 63:

A team member has asked a question about the responsibilities of the Product Manager, QA, and the team regarding quality.

What should the Agile Project Manager advise?

Options:

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.


B.

The entire team is responsible for quality, but each team member's role may vary as stated in the definition of done (DoD).


C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.


D.

Quality is the responsibility of the entire team, and the Product Manager defines the functionality from end to end.


Expert Solution
Questions # 64:

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

Options:

A.

Just-in-time (JIT) refinement


B.

Stories to be released in each sprint


C.

Infrastructure updates


D.

Funding decisions


Expert Solution
Questions # 65:

What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.


B.

Instruct the agile team to fix the user stories during the next retrospective.


C.

Facilitate a user story workshop with the agile team.


D.

Inform the product owner's manager that the work items provide insufficient detail.


Expert Solution
Questions # 66:

A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?

Options:

A.

Resolve the disagreement for the team as a servant leader.


B.

Encourage the team to continue trying to resolve their disagreements.


C.

Advise the team on the correct course of action to avoid disagreements.


D.

Remove the team members that are in disagreement to ensure unity in the team.


Expert Solution
Questions # 67:

Question # 67

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Options:

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.


B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.


C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.


D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.


Expert Solution
Questions # 68:

Question # 68

A scrum master is overseeing the launch of a chatbot for the service desk. Complaints come up post-release about edge case responses to queries. After analyzing the issues, the business decision was made to take the chatbot offline, resulting in workflow disruptions and risking the reputation.

How could this situation have been avoided? (Refer to Testing Protocol Table)

Options:

A.

Conduct user acceptance testing to ensure the chatbot meets stakeholder needs and expectations.


B.

Perform integration testing to minimize any bugs between the chatbot components.


C.

Perform functional testing to verify the chatbot performs the reguired functions.


D.

Conduct regression testing to ensure all previously functioning chatbot features continue to work after updates.


Expert Solution
Questions # 69:

In a project, the customer asks for a requirement that clearly deviates from the contract terms.

How should the contractor react?

Options:

A.

Proceed with the work only after the contract is amended.


B.

Discuss the value of the change for the project with the customer.


C.

Evaluate effort and impact and ask for steering committee and shareholder approval.


D.

Stick with the contract terms and agree to review the requirement if time allows.


Expert Solution
Questions # 70:

A Product Owner new to the role is very enthusiastic about an agile project with an energetic team.

What should be done first to ensure successful delivery of the product?

Options:

A.

Hold a meeting with the team and the Product Owner to develop the team charter, working agreement, guiding principles, and product vision


B.

Ask the Product Owner to create the project vision and charter, and then discuss the guiding principles with the team


C.

Hold a meeting during which the team can present the project charter, high-level project plan, and team values to the Product Owner


D.

Send the Product Owner to formal Product Owner training where the Product Owner can learn how to create a product vision


Expert Solution