PMI-ACP Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

What should the agile team lead do?


A.

Create a central repository for information, and provide access to Team B


B.

Use an information board that will be visible to all passing through the workspace


C.

Email all stakeholders with status updates


D.

Provide Team B with the information on an " as needed " basis