Question #: 64
Topic #: 7

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?


A.

Just-in-time (JIT) refinement


B.

Stories to be released in each sprint


C.

Infrastructure updates


D.

Funding decisions