PMI-ACP Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?


A.

Include security concerns on the agenda for every meeting.


B.

Request that a security expert be added to the team.


C.

Add security as a non-functional requirement to the risk register, and review regularly.


D.

Ensure that planning and prioritizing includes consideration of security requirements.