PMI-ACP Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?


A.

Resolve the disagreement for the team as a servant leader.


B.

Encourage the team to continue trying to resolve their disagreements.


C.

Advise the team on the correct course of action to avoid disagreements.


D.

Remove the team members that are in disagreement to ensure unity in the team.