New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 67 Topic 7 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 67 Topic 7 Discussion

PMI-ACP Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

PMI-ACP Question 67

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)


A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.


B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.


C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.


D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.