Questions # 91:

During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?

Options:

A.

Reduced or improper customer collaboration.


B.

Reduced or improper product knowledge by the development team.


C.

Reduced or improper release planning.


D.

Reduced or improper product specification.


Expert Solution
Questions # 92:

One of the main stakeholders of a project is new to Scrum. The stakeholder asks what to expect in the sprint retrospective.

How should the product owner respond?

Options:

A.

Stakeholders have the opportunity to add features to the sprint.


B.

Team members determine if there are any impediments preventing them from meeting the sprint goal.


C.

The product owner explains which product backlog items have been done and which have not.


D.

Team members identify ways to improve and make plans to implement these improvements.


Expert Solution
Questions # 93:

A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time.

What should the agile facilitator do?

Options:

A.

Dismiss the rest of the team from the meeting to focus on the problem reported by the team member


B.

Ask the team member to wait to discuss until the next daily coordination meeting, the team needs to review the current status.


C.

Inform the team that the meeting will be extended so there is time to hear what the team member is reporting


D.

Stop the team politely and suggest scheduling another meeting to discuss this specific matter.


Expert Solution
Questions # 94:

What should the team do?

Options:

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories


B.

Create a triage step on the Kanban board to pre-identify risky stories


C.

Set a policy to break down stories larger than a specified complexity, then adjust the WIP


D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large


Expert Solution
Questions # 95:

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

Options:

A.

Commit to a specific feature set for delivery


B.

Explain that a commitment will be provided after planning


C.

Have the team estimate in story points to commit to a specific set of features


D.

Use the team's historical velocity to calculate a range of features that can be delivered


Expert Solution
Questions # 96:

What practice is the agile facilitator implementing?

Options:

A.

Building openness and transparency on the project's health and status


B.

Facilitating conflict resolution among executive team members


C.

Using active stakeholder involvement to build features in an incremental and iterative approach


D.

Seeking continuous feedback from executive team members


Expert Solution
Questions # 97:

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals need to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

Options:

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.


B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.


C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.


D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.


Expert Solution
Questions # 98:

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

Options:

A.

Value stream mapping


B.

Long-term Lean planning


C.

Business process modeling


D.

Planning poker


Expert Solution
Questions # 99:

How should the agile team lead respond?

Options:

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.


B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.


C.

Work with the team to create a vision from the stakeholder's supplied requirements.


D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.


Expert Solution
Questions # 100:

A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

Options:

A.

Send the member to training


B.

Ask the outside specialists if database administration is required from the team


C.

Send one member to training only after asking the team if there is an issue with the current workflow


D.

Wait until all members of the team can attend training


Expert Solution