Questions # 121:

A product owner needs to elaborate on a product roadmap. How can the product owner collaborate with stakeholders to identify the features that offer maximum value?

Options:

A.

Identify the product users and their high-level key activities to get their perspective because the product is intended for them.


B.

Obtain the project sponsor's perspective to get an initial idea of the features they believe the product should have to guide the development team.


C.

Analyze the development team's capacity and skills because these will determine which features to include in the roadmap.


D.

Create a draft of the product roadmap that the development team can use as a guide for further guidance.


Expert Solution
Questions # 122:

What is a specific development practice that has been effective in implementing disciplined DevOps?

Options:

A.

Put the client first.


B.

Create a safe environment.


C.

Practice continuous delivery.


D.

Manage risk.


Expert Solution
Questions # 123:

A project team identifies a number of technical challenges with features in the next sprint.

What should they do?

Options:

A.

Request direction from the technical manager


B.

Encourage the Product Owner to reallocate the features to another sprint


C.

Determine who is best qualified to address the challenges


D.

Ask the Product Owner to assign the tasks to the most appropriately skilled resources


Expert Solution
Questions # 124:

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities.

How should the stakeholders ensure their objectives are met by product delivery?

Options:

A.

Provide feedback for completed user stories.


B.

Define how the features will be implemented.


C.

Tell the team which features to include in the backlog.


D.

Write acceptance criteria for the user stories.


Expert Solution
Questions # 125:

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

Options:

A.

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.


B.

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.


C.

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.


D.

Implement a spike to enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working.


Expert Solution
Questions # 126:

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the Scrum Master do?

Options:

A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.


B.

Ask the team to find a workaround so that they can continue with the current project management plan.


C.

Advise the team to continue working on the sprints as the release plan has been set.


D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.


Expert Solution
Questions # 127:

A senior executive contacted an agile lead about starting an agile project to solve a problem for the human resources (HR) department of a company. The project idea is not clear and no backlog has been developed.

How should the agile lead start the project?

Options:

A.

More work is needed to refine the idea and there is no backlog to start working on, so there is no way to help the manager.


B.

Identify the persona that needs help and conduct a workshop applying the empathy map technique about that persona.


C.

Review how similar problems have been resolved in other companies and see if a solution is available on the market.


D.

Start working on a list of user stones to create a backlog and suggest a product owner be assigned to the project.


Expert Solution
Questions # 128:

An organization is shifting to an agile delivery methodology. An agile project manager has been assigned to the transformation project.

What should the agile project manager do to ensure a high level of adoption?

Options:

A.

Focus on not just the "what," but also the "how" of delivering projects.


B.

Ensure that there is buy-in from senior management to adopt agile.


C.

Identify strong product owners to ensure project teams are delivering value.


D.

Train the team on the fundamentals of the agile mindset and principles.


Expert Solution
Questions # 129:

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?

Options:

A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.


B.

Request the team work overtime to get the work done on time and within the allocated budget.


C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.


D.

Review the contract documentation with the customer to clarify the specific agreed-upon budget amount.


Expert Solution
Questions # 130:

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

Options:

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.


B.

They can provide an anticipated date with the assumption that conditions will be ideal.


C.

They can provide a broad range but cannot realistically set a target release date until the team's velocity stabilizes.


D.

They will send an update when all of the stories are estimated and prioritized in the backlog.