PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 125 Topic 13 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 125 Topic 13 Discussion

PMI-ACP Exam Topic 13 Question 125 Discussion:
Question #: 125
Topic #: 13

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?


A.

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.


B.

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.


C.

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.


D.

Implement a spike to enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.