Pass the PMI PMI Agile PMI-ACP Questions and answers with CertsForce

Viewing page 8 out of 15 pages
Viewing questions 71-80 out of questions
Questions # 71:

An agile team wants to collectively determine a project's size. What will the team be doing if they use the planning poker technique to accomplish this?

Options:

A.

Estimating story points by comparing them to similar, past features


B.

Estimating stories by placing them in buckets


C.

Using the number of dots for votes to estimate story points


D.

Estimating the relative size of stories by using story points


Expert Solution
Questions # 72:

In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.

How should the project manager approach this project?

Options:

A.

Define all requirements so value can be added by delivering a high-level plan at the initiation phase.


B.

Suggest the Product Owner prioritize the work items by feature to maximize value.


C.

Ask the customer to define the requirements of all stakeholders and select the most valuable features.


D.

Ensure the client has a clear idea about the features and end product before the project starts.


Expert Solution
Questions # 73:

What should the agile practitioner do next?

Options:

A.

Identify a team member to do a proof of concept using this framework.


B.

Email the team directing them to immediately begin using this new framework.


C.

Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it.


D.

Discuss this option at the next retrospective.


Expert Solution
Questions # 74:

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the Scrum Master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the Scrum Master respond to this request?

Options:

A.

Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.


B.

Create and update bi-weekly project status reports for the stakeholder who requested the report.


C.

Escalate this to the stakeholder's supervisor because this is an unreasonable request.


D.

Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.


Expert Solution
Questions # 75:

After completing the release plan, the team realizes that the project is very likely to have a negative ROI.

What should the team do?

Options:

A.

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI


B.

Replace some team members to reduce the release costs and minimize a negative ROI


C.

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI


D.

Communicate the risk of a negative ROI to the stakeholders, and update the release plan


Expert Solution
Questions # 76:

What should the project team do next?

Options:

A.

Estimate the project team's capacity.


B.

Determine how much work can be delivered.


C.

Calculate how much work will fit into the next iteration.


D.

Estimate items in the product backlog.


Expert Solution
Questions # 77:

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.


B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.


C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.


D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.


Expert Solution
Questions # 78:
Options:

A.

Add new security features to the backlog and prioritize.


B.

Execute a spike to research security features for the project.


C.

Ask questions to determine where and how the product owner wants to use the product.


D.

Ask questions to determine if the product owner can define the desired level of security.


Expert Solution
Questions # 79:
Options:

A.

The increase in velocity and cost


B.

A buffer in the sprint to mitigate unexpected risks


C.

Assigning extra points to each task to allow time for changes


D.

Stories describing infrastructure tasks and analysis tasks


Expert Solution
Questions # 80:

A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.

How should the project manager handle a review with the team member?

Options:

A.

Talk to the team member about project deliverables and how poor performance is unacceptable.


B.

Discuss performance with the team member on the project deliverables and provide constructive feedback.C Inform the learn member that this project is complex and consider moving them to another project


C.

Extend support to the team member as this is the first project in which the team member underperformed.


Expert Solution
Viewing page 8 out of 15 pages
Viewing questions 71-80 out of questions