A complete and realistic backlog must include not onlyfunctional storiesbut alsonon-functional and support taskssuch as infrastructure setup, analysis, and design. ThePMI Agile Practice Guide (Section 5.2: Backlog Composition)andMike Griffiths’ PMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning)emphasize including all types of work in the backlog to ensureaccurate effort planning.
Option Dis correct: effort must includetechnical tasks, not just feature delivery.
Option Asuggests speculation on velocity and cost increases, which is unreliable.
Option BandC(adding buffers or padding estimates) violate agile’s principle of transparency and simplicity.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit