Questions # 31:

An experienced product owner presents the epics and corresponding stories during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master's estimation


B.

Identify a set of user stories based on the team's velocity


C.

Initiate an estimation session


D.

Consult historical data for project completion


Expert Solution
Questions # 32:

During refinement, the team tester has a question about part of the acceptance criteria for a given user story. Who should clarify the acceptance criteria?

Options:

A.

The sponsor, since they understand the business value.


B.

The Scrum Master, since they coordinate with the team and define the acceptance criteria.


C.

The Product Owner, since their vision is the basis for the acceptance criteria.


D.

The developer, since they write the code that would be tested.


Expert Solution
Questions # 33:

An agile team is struggling with an issue. A team member mentions that another team had a similar issue that was resolved, but lessons learned documents are unavailable.

What should the agile practitioner do?

Options:

A.

Suggest that all agile teams share weekly reports on their projects.


B.

Encourage the team to independently find a solution.


C.

Work with the team to create a solution for disseminating team knowledge throughout the company.


D.

Recommend hiring an external expert to advise on the best methods for sharing knowledge among teams.


Expert Solution
Questions # 34:

What is a benefit of this meeting?

Options:

A.

The team will learn how its contribution will create product value


B.

It will enable team acceptance of client priorities


C.

It will enable the team to see the entire project in one glance


D.

It will enable the team to ask any questions to the customer upfront


Expert Solution
Questions # 35:

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

Options:

A.

Set clear expectations and allow everyone to contribute.


B.

Prepare the project vision statement and then present it to the team.


C.

Ask senior management to address the situation.


D.

Seek assistance from the scrum master to mediate the conflict.


Expert Solution
Questions # 36:

Which agile practice would most significantly increase a team's velocity?

Options:

A.

Daily standups


B.

Iteration and release planning


C.

Training in areas of weakness


D.

Iteration


Expert Solution
Questions # 37:

What should the Scrum Master do first?

Options:

A.

Work with the customers to build the product backlog and identify their initial requirements.


B.

Meet with the stakeholders and enterprise architects to understand the project's vision.


C.

Plan and execute a sprint 0 to establish the project's foundational needs.


D.

Create a backlog, and execute a sprint 1 to quickly deliver value to the customers.


Expert Solution
Questions # 38:

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?

Options:

A.

Estimate only functional requirements that will impact product quality


B.

Add team resources


C.

Refer the issue to the product owner


D.

Break non-functional requirements into those that can be delivered in the given sprint


Expert Solution
Questions # 39:

What should the Scrum Master do?

Options:

A.

Engage the team to determine the sprint velocity based on previous agile projects.


B.

Average the sprint velocity based on input from team members


C.

Share the sprint velocity obtained from the sponsor with the team


D.

Run multiple sprints before determining the sprint velocity with the team


Expert Solution
Questions # 40:

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?

Options:

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints


B.

Add risk mitigation time to each requirement


C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation


D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog


Expert Solution