PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 76 Topic 8 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 76 Topic 8 Discussion

PMI-ACP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

What should the project team do next?


A.

Estimate the project team's capacity.


B.

Determine how much work can be delivered.


C.

Calculate how much work will fit into the next iteration.


D.

Estimate items in the product backlog.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.