Theretrospectiveis the agile ceremony designed for teams toinspect and adapttheir process based on actual performance. According to thePMI Agile Practice Guide (Section 5.6: Retrospectives), discussingvelocity issues and delivery concernsduring retrospectives allows the team to collaboratively identify improvement actions.
Mike Griffiths in thePMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning)also notes thatretrospectives are the best settingto discuss variations in velocity and refine estimation or planning practices based on empirical evidence.
Option Cis correct: the retrospective is where the team adapts based on reality.
Option Amay come later but doesn’t address the root issue.
Option Bgoes against agile principles of stable teams and empirical planning.
Option Dis reactive and may mask underlying process issues.