PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 137 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 137 Topic 14 Discussion

PMI-ACP Exam Topic 14 Question 137 Discussion:
Question #: 137
Topic #: 14

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?


A.

Schedule a meeting with the product owner to review the sprint priorities.


B.

Put the high-priority item back into the product backlog.


C.

Extend the sprint end date to accommodate the high-priority item.


D.

Ask the project sponsor to add more resources to ensure timely completion.