The correct answer is D — Help establish the next sprint ' s goal.
The sprint goal provides a shared objective and guides the selection and execution of user stories. It is established collaboratively between the product owner and the development team at the start of sprint planning and precedes task decomposition or estimation.
PMI Agile Practice Guide:
“The team collaborates with the product owner during sprint planning to define a sprint goal. The sprint goal gives the team clarity and focus on what it intends to achieve during the sprint.”
(PMI Agile Practice Guide, Section 5.5 – Iteration Planning)
Mike Griffiths reinforces:
“Effective planning starts with understanding the desired outcome of the sprint. The sprint goal aligns the team and informs prioritization and task breakdown.”
(PMI-ACP Exam Prep, Chapter 5 – Adaptive Planning)
Incorrect options:
A prematurely assigns tasks, which goes against Agile’s collaborative ethos.
B and C happen later in the sprint planning process after defining the sprint goal.
Answer: D
—