PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 129 Topic 13 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 129 Topic 13 Discussion

PMI-ACP Exam Topic 13 Question 129 Discussion:
Question #: 129
Topic #: 13

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?


A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.


B.

Request the team work overtime to get the work done on time and within the allocated budget.


C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.


D.

Review the contract documentation with the customer to clarify the specific agreed-upon budget amount.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.