PMI-ACP Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?


A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.


B.

They can provide an anticipated date with the assumption that conditions will be ideal.


C.

They can provide a broad range but cannot realistically set a target release date until the team's velocity stabilizes.


D.

They will send an update when all of the stories are estimated and prioritized in the backlog.