PMI-ACP Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?


A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.


B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.


C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.


D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.