PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 131 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 131 Topic 14 Discussion

PMI-ACP Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.

What should the Scrum Master do?


A.

Discourage the team member from deviating from the plan and document the request during the retrospective


B.

Encourage the team member to research the issue and present the findings during the retrospective


C.

Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases


D.

Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important