The correct answer is A – Hold a meeting with the team and the Product Owner to develop the team charter, working agreement, guiding principles, and product vision. This collaborative approach fosters shared understanding, ownership, and alignment early in the project.
From the PMI Agile Practice Guide:
“The team chartering process includes developing working agreements, clarifying the product vision, defining team norms, and establishing the team's mission. Early alignment builds trust and commitment.”
(PMI Agile Practice Guide, Section 4.3 – Team Charter and Working Agreements)
Mike Griffiths elaborates:
“A strong start includes co-creating team values, the product vision, and working agreements. Doing this together builds a strong foundation for delivery.”
(Mike Griffiths, PMI-ACP Exam Prep, Chapter 2 – Agile Principles and Chapter 4 – Team Formation)
Incorrect options:
B separates the Product Owner from the team early on.
C reverses the roles—vision should be owned by the Product Owner.
D is helpful, but not a prerequisite for team alignment and success.
Answer: A