New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 55 Topic 6 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 55 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

What should the agile project manager do?


A.

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.


B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.


C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.


D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.