Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 54 Topic 6 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 54 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 54 Discussion:
Question #: 54
Topic #: 6

What can an agile practitioner conclude about team A and team B ' s estimates?


A.

Team B has underestimated scope compared to team A.


B.

Team A is more confident in delivering velocity than team B.


C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.


D.

Both teams have estimated the project to be of same size.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.