PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 53 Topic 6 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 53 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.

How should the team lead address this?


A.

Inform management and suggest that additional resources may be required


B.

Discuss the issue with the team in the daily stand-up meetings


C.

Meet personally with the stressed team member to brainstorm ways to better manage their time


D.

Begin tracking the stressed team member's tasks in a separate backlog for additional analysis and reporting


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.